Calculating and Approving the Calc Summary

The Calc Summary must be calculated and Final Approved. This way the Schedule is credited, and a new Corrosion Schedule is created with the new NID.

To calculate the data:

  • Click the calculate button to calculate the NID.
Graphical user interface, application  Description automatically generatedClick the Calculate button.

To Approve the Calc Summary:

  • Click the Approve button to open the Approve section.
Graphical user interface, application  Description automatically generatedClick the Approve button.

 

  • Click Approve to Final Approve the Calc Summary. Note: This creates an inspection event for the MS.
Click Approve.

 

  • The Corrosion Schedule of the Circuit will be credited and a new NID will be set. Also, if the Circuit is inherited to an RBI Component, the Calc Summary will automatically be applied in the RBI Analysis Inspection History tab, to update the RBI LID.

For more information on the recalculations and the final approval process see Approving Corrosion Circuit Calculations.