--- title: "Data Quantification RBI Analysis Criteria" slug: "data-quantification-rbi-analysis-component-criteria" tags: ["Components", "Analysis", "S-RBI", "Dashboards"] updated: 2026-10-27T23:11:28Z published: 2026-10-27T23:11:28Z canonical: "ims-handbook.cenosco.com/data-quantification-rbi-analysis-component-criteria" --- > ## Documentation Index > Fetch the complete documentation index at: https://ims-handbook.cenosco.com/llms.txt > Use this file to discover all available pages before exploring further. # Data Quantification RBI Analysis (Component) Criteria This article explains in detail the RBI Analysis criteria (referring to RBI Components) for the Data Quantification Section on the [RBI Dashboard](/v414/docs/rbi-dashboard-2). To learn about the other criteria see [RBI Dashboard Data Quantification](/v414/docs/rbi-dashboard-data-quantification). ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-NG3W68H6.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ### Baseline Baseline Components must adhere to the following criteria: - The Component type may not be *GENERAL* - Both the Component and Equipment must be Active - Equipment Status must be *In Service* or *In Construction* - Equipment Perform RBI must be checked ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-3MI4XPO1.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ### RBI components with only scenarios or no assessment Stage I Components must meet Baseline criteria. ### RBI components with scenarios and consequence assessments Stage II Components must adhere to the following criteria: - Components must meet Stage I criteria - Components must have at least one unexpired analysis and at least one of the following two criteria must be met: 1. Analysis performed for the *NON-CORROSIVE* Degradation mechanism 2. or the Scenario must be filled in and at least one of the consequences assessments must be performed ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-QBG11YLF.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-F49FO3EO.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ### RBI components with Stage 2 and with StF assessments Stage III Components must adhere to the following criteria: - Components must meet Stage II criteria - At least one of the following two criteria must be met: 1. Analysis performed for the *NON-CORROSIVE* Degradation mechanism 2. or StF assessment has to be performed ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-VFWHH37E.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ### RBI components with Stage 3 and with confidence assessments (corrosive injection and mix points, corrosive deadlegs counted as complete) Stage IV Components must adhere to the following criteria: - Components must meet Stage III criteria - At least one of the following two criteria must be met: 1. Analysis performed for the *NON-CORROSIVE* or any of the strategy-based Degradation mechanisms 2. or the Confidence assessment has been performed 3. or Component type is set to any of the following: *CORROSIVE INJECTION POINT*, *CORROSIVE MIXING POINT,* *CORROSIVE DEADLEG* ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-V00NR60N.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) ### RBI components with Stage 4 and with Next Inspection Dates with final approved schedule or corrosion circuit Stage V Components must adhere to the following criteria: - Components must meet Stage IV criteria - At least one of the following two sets of criteria must be met: ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-NF44MZWT.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D) 1. Components are in Schedule scope - The Component must be in the scope of a final approved, uncredited Schedule - Analysis must have either RBI NID calculated or an Inspection Strategy - Analysis status must be *Analysis completed, implemented* 1. Component inherited on a Circuit - Components must be inherited on a Circuit with a final approved Calc Summary - Analysis status must be *Analysis completed, implemented* ![](https://cdn.document360.io/e492a0e0-a4ba-4aca-8fc6-76b95f91fdf3/Images/Documentation/image-L5TEPEKG.png?sv=2026-02-06&spr=https&st=2026-11-07T16%3A39%3A52Z&se=2026-11-07T17%3A39%3A52Z&sr=c&sp=r&sig=5C8rWEUc2VuKVRNI7w4TGhDGiEz3WQqzcJAc4N%2B88qI%3D)