In PLSS, Schedules are created at the Equipment level. A Schedule contains information on:
- When to perform an activity.
- What to do.
- How to do it.
In PLSS four Schedule Types have been implemented. A Schedule can be created for:
- An Inspection (ILI run, collect CP data, …).
- An Assessment (RBA Assessment, Internal Corrosion Assessment, …).
- A Corrective Action (a once-off activity).
- Preventative Maintenance (cleaning pigging, hydrotest, …).
After selecting the Schedule Type, the “What to do” has to be specified by:
- selecting the Scope, for example, Overland Survey, Pigging, or Sampling, ….and,
- selecting the corresponding Plan for that Scope by clicking on "What is planned?" For example, "CP Test Post Survey" is a Plan for the Scope "Overlay Survey".
More information on “How to do” the activity, can be specified in the sections Narrative, Tasks, or Attachments.
So, each Schedule contains:
- A Date, before the Schedule / activity has to be executed.
- A Scope depending on Schedule Type.
- One or more Plan Codes depending on the Scope.
- A Narrative, with a more detailed description of the work.
- Attachments, optional.
After the activity (activities) in the Schedule has been executed, the results will be stored in IMS-PLSS and the Schedule should be credited in the ECH. See Creating Schedules.
Schedule information can be sent to SAP if the interface to SAP is switched on.
To learn more about Schedules see: IMS Schedules (across Disciplines).