• Beta
MEC Optimization 'ToR HDS-MEC'
  • 09 Aug 2024
  • 9 Minutes to read
  • Contributors
  • Dark
    Light
  • PDF

MEC Optimization 'ToR HDS-MEC'

  • Dark
    Light
  • PDF

Article summary

Here an example ToR (Terms of Reference) document is provided to guide IMS RCM users in the MEC optimization activity. This document provides the inputs and sets the expectations to MEC Optimization. 

Terms of Reference for an IMS-RCM study of an HDS unit

Introduction

After an initial RCM study was completed for the HDS (Hydro desulphurization) unit in the Westland Refinery, a series of small updates were applied over the years. As there was a quite a turnover of Reliability engineers, these modifications and updates led to inconsistency in the study. Although the business performance of the unit has been improved initially, management now expects that the TA interval of the unit to be firmed up to 4 years and to reduce total maintenance expenses (incl. TA) in line with Q1/Q2 of the benchmark.

It is further proposed to create a tighter connect between the activities specified by the RCM study and the annual preventive maintenance budgeting rounds, leading to an activity-based budgeting.

This Terms of Reference provides the plan for the MEC optimization of the HDS RCM study review, approved for execution by the Unified Petrol Reliability Manager, justifying the work to be done, the resources to be used and results to be reported out.

RCM and MEC optimization

RCM is a structured and multidisciplinary decision support process to effectively document the optimum maintenance requirements of physical assets in their operating context. The output of the RCM study is used for MEC optimization where the specified activities will be aligned later with other studying processes like PEI and SIS, to optimize Operational Availability and reduce cost via reduction of double work, improvement of effectiveness and efficiency.

For this MEC review the targets are:

  • The RCM Analysis should bring the plant availability of the HDS unit from the quartile 4 performance to quartile 1/2 performance according last Solomon study.
  • High priority repairs should reduce from 20% (Prio 1+2) to 5%.
  • The MEC optimization should deliver a Turnaround interval of 4 years.
  • Equipment with a criticality of M-level or higher are RCM analyzed in detail.
  • Residual risk should be M-level or lower.
  • An MEI score lower than 1 will be ‘run to failure’.
  • The MEI score should preferably be larger than 2.
  • The maintenance activities should be presented to enable efficient execution, where tasks that can be efficiently executed together are presented in groups.
  • The MEC optimization is to be executed in the IMS web-tool when updates from the RCM, PEI and/or SIS studies are issued.

Plant data

The plant studied is HDS Unit, a catalytic chemical process to remove Sulphur (S) from diesel at 17500 Barrels per Day (2059t/d @ 740kg/m3). This plant has had some upgrades including new catalyst which is more reactive and requests a lower process temperature and pressure.

To reduce the Sulphur dioxide emissions from diesel in automotive vehicles, legal conditions demand a 50ppm Sulphur specification on the fuel, which has pushed the margin up to 300$/ton. The product loss equation for downtime of this unit is: 2059t/d x 300$/t = 617,710$/d or 25,740$/hr. There is no holdup or tankage in the System so any downtime results directly into production loss. In case of a plant-trip there is 4 hrs. extra downtime to recover production on specification.

Hydro-treating is a process to catalytically stabilize petroleum products by converting olefins to paraffin’s or remove objectionable elements from products or feedstock by reacting them with hydrogen.

The plant upgrades also led to new burners and furnace control System to reduce emissions and increase production. The upgraded burner control System is setup as a separate RCM functional System in IMS, including safeguarding Systems with instrumented protective functions.

Value levers

Current operational availability of the unit is 92.7% and 92.5% over last two turnarounds, which is in the quartile 4 group of the benchmark shown by Solomon studies.

Improvement is aimed for to reach 97% operational availability which should give a benefit of 6M$/yr. These improvements need to come from improved maintenance strategies on the HDS reactor, the recycle gas compressor, the furnace and heat exchangers, and the pumps in the unit.

The unit is subdivided into 4 functional Systems: Reaction section, Stripper section, Gas recycle section and Burner control System.

Function of the Reaction section is to treat 85t/h diesel and remove 99.9% Sulphur.

Functional failures of the Reaction System causing production loss are:

  • Less than 85t/h diesel throughput of the System
  • Unable to heat the product to 350°C at 85t/h.
  • Unable to remove 99.9% Sulphur
  • Product leakages with high H2S content causing plot clear.

The function of the Stripper section is to treat 85t/h diesel and remove 99.9% Sulphur/H2S.

Functional failures of the Stripper System causing production loss are:

  • Less than 85t/h diesel throughput of the System
  • Unable to heat the feed of 15.4t/h to 170°C at reboiler
  • Unable to keep stripper top temperature to 35°C
  • Product leakages with high H2S content causing plot clear.

The function of the Recycle gas section is to feed H2 rich gas to the high-pressure feed stream.

Functional failures of the Recycle gas System causing production loss are:

  • Compressor fails to deliver discharge pressure at rated gas-flow (2400Nm3/hr.)
  • High H2S content causing plot clear around the compressor (and off-spec purge gas).
  • Product leakages with high H2S content causing plot clear.

The function of the Burner Control Fired heater section is to warm 85 t/h diesel from 250°C to 420°C respecting production plan and 'License to operate'.

Functional failures of the Recycle gas System are:

  • Unable to warm 85t/h diesel from 250°C to 420°C
  • High soot, High CO-CO2
  • Unable to reach a 4y TA interval

The main Equipment in the HDS unit relevant for the RCM study are distributed of these four Systems with a total 58 Equipment and 24 Flocs.


An IMS-RBI study for the HDS unit is on the year plan for next year with implementation completed on the following year. Some pressurized Equipment do have inspection schedules attached. No SIFpro study is done.

Current maintenance activities involved are:

Pumps: These are typically 1-out-of-2 redundancy set ups and checked by operations as they are involved in the operator rounds to report issues. Operations take care of the main and stand-by pump operation. Current performance is a MTBM of 3.1 years with many seal failures and bearing failures. Also often the A and B pump are reported defect close after each other. Pump failures contribute for 33% to the unplanned downtime.

Compressor: A single installed reciprocating compressor that is E-motor driven and is continuously running. It is checked by operations through the operator rounds to report issues. Current performance is a MTBM of 1.3 years with many valve and piston failures. The compressor failures contribute for 35% to the unplanned downtime.

Heat Exchangers: These are inspected in each TA and the recommendations from Inspection are followed up. Little corrosion involved, no external leakages reported. Current performance is that operations are unhappy with the heat exchangers and that there are often internal leakages and fouling involved. Inspection does not report fouling and requires cleaning for inspection. The heat exchanger failures contribute for 10% to the downtime.

Fired heater: The heater suffering from many trips. The furnace is inspected in each TA and the recommendations from Inspection are followed up. Little corrosion involved, no external leakages reported. Current performance is that end of run (close to next TA) operations has difficulty to heat the unit sufficiently. Inspection does not report fouling and requires cleaning for inspection. The fired heater failures contribute for 13% to the downtime and drives the TA interval.

Reactor: The reactor is inspected in each TA and the recommendations from Inspection are followed up. Little corrosion involved, no external leakages reported. The chemical performance of the reactor is monitored every month, based on the lab analyses. The catalyst is renewed after 3-4 TA’s. In the last run of the catalyst the pressure drop over the reactor reaches the maximum pressure drop value leading to 10-15% reduced throughput, contributing to 5% of the production loss.

Pressure regulator: The control-valve is overhauled each TA although causing problems after each start-up. After 3-4 month in the TA-run the valve functions well, but has caused 5-10% lost production by then, contributing to 5% of the unit’s production loss.

Columns: The columns are inspected in each TA and the recommendations from Inspection are followed up. Little corrosion involved, no external leakages reported. Every other TA there has been an issue with one of the columns, basically by poor maintenance from contractor workers causing internals to malfunction.

Vessels: The vessels – which are actually separators - are inspected in each TA and the recommendations from Inspection are followed up. Little corrosion involved, no external leakages reported. Each TA there has been an issue with one of the vessels, basically caused by shortcomings with the internals.

HDS Downtime

The downtime of the HDS plant is given in operational availability 92.7% and 92.5% over last two Turnarounds (TA’s). Current TA’s have a 2 year cycle with almost 4 weeks downtime.
The main planned activities in the TA are inspections of the reactor and the heat-exchangers (with associated repair/ restoration work) ; and overhaul of the recycle-gas compressor.
The main unplanned downtime come forward from many pump breakdowns and compressor trips.
With this downtime the HDS is in the bottom quartile of the benchmark, where the ambition is to reach quartile 2 of the benchmark with an operational availability of 97%.

This table shows the current downtime and available of the HDS plant.

The ambition is to mover to a 4 years TA cycle and a 97% operational availability, with slightly reduced TA duration, and a reduction of on-planned downtime 13 days/year to 5 days/year by improved reliability of the pumps.


This table shows the desired downtime of the HDS plant after improvements made. 

Currently there is approval to repair all pumps on high priority, despite this approach the availability of the pumps in the unit is poor leading to frequent (short) downtime.

Asset Register HDS unit (Unit-X)

Floc IdFloc DescriptionLocation TypeSAP TypeEq IDSAP TypeEq Type

03FC24-Ux

Comb. air flow controller

FLOW-FLOC

I_FLO_VENT




03FCV24-Ux

Comb. air flow valve

CONTROL VALVE-FLOC


03FCV24-Ux-eq

I_CVL_BUTR

CONTROL VALVE

03FIC22-Ux

Fuel Oil feed Flow

FLOW-FLOC

I_FLO_DPSM




03FZA26-Ux

Min. flow trip stream 1

FLOW-FLOC

I_FLO_DPSI




03FZA27-Ux

Min. flow trip stream 2

FLOW-FLOC

I_FLO_DPSI




03FZA28-Ux

Min. flow trip stream 3

FLOW-FLOC

I_FLO_DPSI




03FZA29-Ux

Min. flow trip stream 4

FLOW-FLOC

I_FLO_DPSI




03FZA30-Ux

Comb. air Min. flow trip

FLOW-FLOC

I_FLO_DPSI




03HS13-Ux

Reset from minimal firing

SWITCH-FLOC

I_SWI_X




03HZ51-Ux

Furnace start - fuel open

SWITCH-FLOC

I_SWI_X




03HZA16-Ux

Man. ShutDown - CR

SWITCH-FLOC

I_SWI_X




03HZA17-Ux

Man. ShutDown - Local

SWITCH-FLOC

I_SWI_X




03PCV24-Ux

Flue gas damper valve

CONTROL VALVE-FLOC


03PCV24-Ux-eq

I_CVL_BUTR

CONTROL VALVE

03PDIC073-Ux

Atom.steam pr.cntr.

PRESSURE-FLOC

I_PRE_DISM




03PI23-Ux

Fire box pressure

PRESSURE-FLOC

I_PRE_ABSM




03PIC75-Ux

Mx Firing Pr. control

PRESSURE-FLOC

I_PRE_ABSM




03PIC76-Ux

Min.Firing Pr.control

PRESSURE-FLOC

I_PRE_ABSM




03PICV76-Ux

Min.Firing Pr.control vlv

CONTROL VALVE-FLOC


03PICV76-Ux-eq

I_CVL_GLOB

CONTROL VALVE

03PZA71-Ux

Mx. Firing Pressure trip

PRESSURE-FLOC

I_PRE_ABSM




03PZA77-Ux

Ato.steam pr.low

PRESSURE-FLOC

I_PRE_ABSM




03QRA10-Ux

Flue gas O2

ANALYSER-FLOC


03QRA10-Ux-eq

I_QMI_OXYG

ANALYSER

03TC46-Ux

Furn. output temp. Cntr.

TEMPERATURE-FLOC

I_TEM_TC




03TIZA50a-Ux

Furn. output temp. trip a

TEMPERATURE-FLOC

I_TEM_TC




03TIZA50b-Ux

Furn. output temp. trip b

TEMPERATURE-FLOC

I_TEM_TC




03TIZA50c-Ux

Furn. output temp. trip c

TEMPERATURE-FLOC

I_TEM_TC




03TRCA43-Ux

Air pre-h.temp. controler

TEMPERATURE-FLOC

I_TEM_TC




03UZ11-Ux

Fuel to bruner 1

CONTROL VALVE-FLOC


03UZ11-Ux-eq

I_CVL_TBAL

CONTROL VALVE

03UZ12-Ux

Fuel to bruner 2

CONTROL VALVE-FLOC


03UZ12-Ux-eq

I_CVL_TBAL

CONTROL VALVE

03UZ13-Ux

Fuel to bruner 3

CONTROL VALVE-FLOC


03UZ13-Ux-eq

I_CVL_TBAL

CONTROL VALVE

03UZ14-Ux

Fuel to bruner 4

CONTROL VALVE-FLOC


03UZ14-Ux-eq

I_CVL_TBAL

CONTROL VALVE

03UZV10-Ux

Furnace trip valve

CONTROL VALVE-FLOC


03UZV10-Ux-eq

I_CVL_TBAL

CONTROL VALVE

03XZA41-Ux

Flame eye 1 B1

ANALYSER-FLOC


03XZA41-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA42-Ux

Flame eye 1 B2

ANALYSER-FLOC


03XZA42-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA43-Ux

Flame eye 1 B3

ANALYSER-FLOC


03XZA43-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA44-Ux

Flame eye 1 B4

ANALYSER-FLOC


03XZA44-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA45-Ux

Flame eye 2 B1

ANALYSER-FLOC


03XZA45-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA46-Ux

Flame eye 2 B2

ANALYSER-FLOC


03XZA46-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA47-Ux

Flame eye 2 B3

ANALYSER-FLOC


03XZA47-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA48-Ux

Flame eye 2 B4

ANALYSER-FLOC


03XZA48-Ux-eq

I_QMI_FLAM

ANALYSER

03XZA53-Ux

Air-Fuel ratio low trip

CONTROLLER-FLOC

C_CTR_SAFE




1PC01-Ux

Pressure regulator

CONTROL VALVE-FLOC


1PC01-eq-Ux

I_CVL_GLOB

CONTROL VALVE

Floc IdFloc DescriptionLocation TypeSAP Type Eq IDSAP TypeEq Type

B310-Ux

Comb. air fan

ROTATING-FLOC


B310-Ux-eq

M_ROT_FAN

ROTATING

B311-Ux

Flue gas fan

ROTATING-FLOC


B311-Ux-eq

M_ROT_FAN

ROTATING

C101-Ux

Amine contactor

VESSEL-FLOC

M_COL_PACK

C101-Ux-eq

M_COL_PACK

VESSEL

C102-Ux

Stripper column

VESSEL-FLOC


C102-eq-Ux

M_COL_PACK

VESSEL

E101A-Ux

Feed heat exchanger A

EXCHANGER-FLOC


E101A-eq-Ux

M_XCH_BUN

BUNDLE

E101A-Ux

Feed heat exchanger A

EXCHANGER-FLOC


E101S-eq-Ux

M_XCH_BUN

BUNDLE

E101B-Ux

Feed heat exchanger B

EXCHANGER-FLOC


E101B-eq-Ux

M_XCH_BUN

BUNDLE

E102-Ux

Cooler cooling water

EXCHANGER-FLOC


E102-eq-Ux

M_XCH_BUN

BUNDLE

E103-Ux

Reboiler

EXCHANGER-FLOC


E103-eq-Ux

M_XCH_BUN

BUNDLE

E104-Ux

Top condenser CW

EXCHANGER-FLOC


E104-eq-Ux

M_XCH_BUN

BUNDLE

E117-Ux

Air pre heater (fluegas)

FURNACE-FLOC


E117-Ux-eq

M_FUR_PREH

FURNACE

E118-Ux

Air pre heater (steam)

FURNACE-FLOC


E118-Ux-eq

M_FUR_PREH

FURNACE

F101-Ux

Fired heater

FURNACE-FLOC


F101-burn-Ux

M_FUR_BURN

FURNACE

F101-Ux

Fired heater

FURNACE-FLOC


F101-conv-Ux

M_FUR_CONV

FURNACE

F101-Ux

Fired heater

FURNACE-FLOC


F101-radi-Ux

M_FUR_RADI

FURNACE

K101-Ux

Recycle gas compressor

COMPRESSOR-FLOC

M_COM_RECI

K101-eq-Ux

M_COM_RECI

COMPRESSOR

P101A-Ux

Feed pump main

PUMP-FLOC


P101A-eq-Ux

M_PUM_CENH

PUMP

P101B-Ux

Feed pump stand-by

PUMP-FLOC


P101B-eq-Ux

M_PUM_CENH

PUMP

P102A-Ux

Reflux pump main

PUMP-FLOC


P102A-eq-Ux

M_PUM_CENH

PUMP

P102B-Ux

Reflux pump stand by

PUMP-FLOC


P102B-eq-Ux

M_PUM_CENH

PUMP

PUxA-Ux

Pump motor main

MOTOR-FLOC


PUxA-eq-Ux

E_MOT_LV

MOTOR

PUxB-Ux

Pump motor stand by

MOTOR-FLOC


PUxB-eq-Ux

E_MOT_LV

MOTOR

PM102A-Ux

Pump motor main

MOTOR-FLOC


PM102A-eq-Ux

E_MOT_LV

MOTOR

PM102B-Ux

Pump motor stand by

MOTOR-FLOC


PM102B-eq-Ux

E_MOT_LV

MOTOR

R101-Ux

Fixed bed reactor

VESSEL-FLOC


R101-eq-Ux

M_VES_REAC

VESSEL

V101-Ux

Gas separator

VESSEL-FLOC


V101-eq-Ux

M_VES_SEP

VESSEL

V102-Ux

Reflux drum

VESSEL-FLOC


V102-eq-Ux

M_VES_SEP

VESSEL

RCM Methodology References

For further background and details on RCM Analysis these key documents are referred to:

  1. RRM S-RCM Manual, Shell Global Sol. V2 OG 04-30260
  2. RCM II book by John Moubray; ISBN 9780831131463
  3. SAE JA1011, Evaluation criteria for Reliability Centered Maintenance (RCM) Process
  4. SAE JA1012, A guide to the Reliability Centered Maintenance (RCM) Standard
  5. ISO 60300-3-11, Application guide Reliability centered maintenance
  6. ISO 14224; Collection and Exchange of reliability and maintenance data for Equipment
  7. IEC 60812; Analysis techniques for System reliability – Procedure for Failure Mode and effects Analysis (FMEA)

Was this helpful? Click to add feedback comments

Changing your password will log you out immediately. Use the new password to log back in.
First name must have atleast 2 characters. Numbers and special characters are not allowed.
Last name must have atleast 1 characters. Numbers and special characters are not allowed.
Enter a valid email
Enter a valid password
Your profile has been successfully updated.
ESC

Eddy AI, facilitating knowledge discovery through conversational intelligence