PEI Schedule NID Calculation - Example
Schedule Next Inspection Date (or NID) is calculated based on the Horserace approach. This article aims to provide a detailed example of a NID calculation. Schedule NID [14] is determined as the soonest coming date (winner of the horse race) from a selection of dates that can be found on the Schedule Inspection event.
Take Note
The numbers in brackets refer to positions on bellow attached screenshots.
User Date
See [5]
The user is allowed to set the User Date as any date in the future.
The intent of the User Date is to allow the user to influence the Schedule NID for the first iteration of the Schedule.
Take Note
The User Date is mandatory if no other Date is provided on the Schedule.
Event Date
See [6]
This date is coming from the linked Planned event, if one has been linked to the Schedule.
Event Date will update automatically when the linked Planned event has its Event NID updated.
Event Date is no longer shown here. It is now shown in the Details section and does not take part in the horserace for the NID.
Take Note
The Event Date has been moved to the Details section and no longer takes part in the horserace for the NID.
RBI Next Insp. Date
See [7]
This date comes from a completed RBI Analysis that may be linked to the Schedule via the Component.
This date will be updated automatically when the RBI NID is updated. The Schedule will be set to Draft when that occurs.
Take Note
RBI NID will not have an effect when Ignore RBI Interval/NID [2] is checked.
The checkbox does not apply to Corrosion Schedules.
Take note
To update RBI NID, the RBI engineer will need to apply a new inspection date through Inspection History.
Time interval
See [11]
The Time interval [11] is calculated on recurring Schedules to allow the Time Interval Date [11] to be calculated.
The Time interval [11] is determined as the lowest number of months from the following: User interval [8], Max interval [9], RBI Interval (MII) [10].
User interval
See [8]
Users are allowed to set the User interval [8] arbitrarily (up to 24000 months).
Take Note
The User interval [8] is mandatory if no other interval is specified on a recurring Schedule.
Max interval
See [9]
This interval is coming from the Inspection Default Settings and is selected based on the Hierarchy type, Schedule Inspection type and the Inspection reason.
Take Note
The Exceed Max checkbox allows users to override the Max interval [9] value.
RBI Interval (MII)
See [10]
This interval is coming from a completed RBI Analysis that may be linked to the Schedule via the Component.
This interval will be updated automatically when the RBI MII is updated. The Schedule will be set to Draft when that occurs.
RBI MII will not have an effect when Ignore RBI Interval/NID [2] is checked.
Time Interval Date
See [12]
This date is calculated based on the Last Insp. Date [4] (LID) and the Calculated Interval.
Time Interval Date [12] must always be present on recurring Schedules.
If the Schedule has not been created on an ECH or after approving a Corrosion Inspection, the Created Date [1] will replace the LID as the basis of the Time Interval Date calculation.
Calculated NID
See [13]
Applicable only on Corrosion Schedules.
Calculated Interval and Calculated NID [13] are coming from the Corrosion Calc summary.
Take Note
Depending on the discrepancy between the Corrosion Schedule LID (based on the last valid Inspection Date) and the Calc summary LID (based on the Inspection Date where the leading CML measurement was taken), the Calculated Interval, as shown on the Corrosion Schedule, may be recalculated and thus differ from one shown on the Calc summary.
For more information on the Horserace calculations see PEI Next Inspection Date (NID) - Horserace