Step 9 Determine Next Inspection Date (AR) and link to Inspection Schedule (Civil)

  • Dark
    Light
  • PDF

Article summary

For Age-Related DMs a NID is calculated and it can the be assigned to an Inspection Schedule.

Methodology

Maximum Inspection Interval

The risk-based Maximum Inspection Interval (MII) is calculated as follows:

Maximum Inspection Interval = [Interval Factor x Remnant Life]

Thus, the inspection interval depends on the best estimate for the Remnant Life (RL) based on findings of the last inspection. This estimate is to be revised based on every new set of inspection data. Therefore, there is not fixed inspection interval, but it will be adjusted periodically, based on the latest inspection findings. The latest inspection provides a new last inspection date and an updated estimate for the Remnant Functional Life.

In practice this may not be immediately after every inspection, but this should not be postponed to long. For example, a monthly review cycle may be appropriate in which all inspection findings from the previous month are considered.

Next Inspection Date

The Next Inspection Date is determined taking the last inspection date as the starting point. The inspection interval is added to this last date, as illustrated in the figure.

The inspection interval is added to this last date to determine the NID. 

Assign the RBI assessment to an Inspection Schedule Scope

The RBI assessment outcome can be added to the scope of an existing recurring inspection schedule. In this way the inspector will make sure to check RBI damage mechanisms during the inspection and the RBI MII/NID will become a factor in the schedule interval. Also crediting of this schedule will now automatically update your RBI inspection history, thus you will not need to Apply the ECH manually.

Software

For more detail on Schedules (including CAIRs), refer to PEI Schedules.

Review Risk Based Inspection Results (AR)

  • Click the NID tab to review Inspection Interval and Next inspection date.Review the NID.

Assign the RBI assessment to an Inspection Schedule Scope (AR)

  • Select the Component – DM combination.
  • Click the target icon in the Add to scope column.

Add to Schedule Scope.

  • A pop-up will appear. Select the schedule.

Select Schedule to which RBI NID must be added.Select Schedule to which RBI NID must be added.

  • Click Save and close the modal dialog.

Verify that the Schedule has the RBI assessment in scope and Approve the Schedule:

  • Click on the Inspection Schedule ID in the Schedules List.
  • Verify that the RBI assessment is in scope.
  • Verify that the RBI Interval (MII) is included.
  • Click Approve.
  • Enter a reason, e.g. “RBI added to scope”.
Verify that the RBI Interval (MII) is included in the Schedule Scope.

 


Was this helpful? Click to add feedback comments

Changing your password will log you out immediately. Use the new password to log back in.
First name must have atleast 2 characters. Numbers and special characters are not allowed.
Last name must have atleast 1 characters. Numbers and special characters are not allowed.
Enter a valid email
Enter a valid password
Your profile has been successfully updated.
ESC

Eddy AI, facilitating knowledge discovery through conversational intelligence