Version 2022.1 brings updates to existing TAT features, mostly focused on new checklists and a new dashboard. It also brings existing IMS functionality to TAT: a Planned Events Main grid, bulk approval, and bulk report generation.


Highlights

New Checklists

IMSFB-28882

IMSFB-28883

The new IMS Dynamic Forms are now available for TAT. This enables new Checklists, which makes it still easier to capture findings and track progress. In addition to the existing Checklists, new Checklists are available for Vessels, Exchangers and Columns. These new Checklists are organized into 3 Stages: First Inspection, Intermediate Inspection, and Final Inspection. Completeness, Issues and Progress are all tracked per Stage.

Graphical user interface, application, email  Description automatically generatedFigure 1: A new Checklist with Stages.

When a Stage is opened, the same questions, as in the previously used Checklists, will show. The new Checklists enable Observation capturing for each finding. If everything is ok, users can click the “All Acceptable” button to instantaneously set all the values in the Stage to a good condition.

Graphical user interface, text, website  Description automatically generatedFigure 2: A new Checklist showing filled in questions and one captured Observation.

When the inspection is done, users can create a report in which the findings (answers) will now be color coded and organized per inspection.

Table  Description automatically generatedFigure 3: A report generated from the Condition History.

All the Checklists are available in Custom reports. These Checklists can easily be cloned and adjusted for different cases.

New Dashboard showing Condition History Statuses

IMSFB-26995

TAT now has a new Dashboard to track Turnaround efforts. The Dashboard can easily be cloned and modified for any Turnaround.

On the right the Dashboard shows Condition Histories, grouped based on their Status. Users can also see how many Condition Histories are open and how many must be reviewed before closing, together with other relevant information. On the left the Dashboard shows Schedules. Here users can see how many Schedules are in scope of a Condition History, together with other relevant information.

The previous legacy Dashboard will be retired.

Graphical user interface  Description automatically generatedFigure 4: The new Turnaround Dashboard.

Planned Events Main Screen grid

TAT now shows the list of Turnarounds (Planned Events) in a Main Screen grid. Previously this list was only available in settings.

It is also now possible to open Planned Event Detail Pages. This will show which Schedules and Equipment are included in the TA scope.

To make this Main Screen grid visible, users must go to “My Account” and click Edit. In “Main Grid Settings” they can then enable the “Planned Events” Main Screen.

Graphical user interface, application, table  Description automatically generatedFigure 5: Enabling the Planned Events Main Screen grid.

After saving the change, the new Planned Events Main Screen grid will be available.

Figure 6: The Planned Events Menu will be visible after enabling it.

All TAs (Planned Events) in the system will be listed in the Planned Events grid, regardless of if they were created in PEI or some other module.

Graphical user interface, application, table, Excel  Description automatically generatedFigure 7: The Planned Events Main Screen grid.

When a Planned Event is opened (by clicking on the name hyper link), users will be directed to the Details Page where the in-scope Schedules and Condition Histories created in TAT, will show.

Graphical user interface, table  Description automatically generatedFigure 8: Overview of the Schedules and Condition Histories in a Planned Event’s scope.

Other TAT Improvements

Adjusted Condition History Report

IMSFB-19898

To support the existing way of working with codes, the Condition History report has been changed to better represent the inspection findings. Findings are now grouped per inspection to communicate the findings more clearly.

Table  Description automatically generatedFigure 9: A Condition History Report showing grouped findings. 

Bulk Approval and Bulk Report Generation for Condition Histories

It is now possible to bulk approve Condition Histories, as well as bulk generate Condition History reports, from the Condition History Main Screen. Previously each Condition History had the be Approved individually. Also, only individual report creation was possible. The Bulk Approve button is available in the toolbar under “Inspections” and the Bulk Report Generation button is available under “Import/ Export”.

Graphical user interface  Description automatically generated with medium confidenceFigure 10: The Bulk Approve and Bulk Report Generation buttons for Condition Histories. 

 Resolved issues

Module
Count

ECH

2

Schedule

1

Total

3