Aim
The S-RBI deliverables are:
- A Next Inspection Date (NID) – mainly for AR DMs.
- An Inspection Strategy (IS) and sometimes Maximum Inspection Interval (MII) – for NAR DMs.
- A required Inspection Effectiveness* – for AR DMs. The user can use the S-RBI results (Interval Factor (IF) and Remnant Life (RL)) to determine this. The required Inspection Effectiveness then in turn determines the required combination of Inspection technique and coverage.
*Note: According to API RP 581.
These 3 deliverables determine how and when to inspect, i.e., how to verify the Barriers, and should be reviewed and interpreted, before being assigned to an inspection in Step 12.
See Methodology Step 11 and Software Step 11.