- Print
- DarkLight
- PDF
There are several places in the application from where you can add a new ECH, for example:
Section | Screenshot |
---|---|
(Header bar) | |
(Side info bar) | |
(Condition History section) | |
Schedules Details Page header. Note: In this case the current Schedule will be added to the ECH scope. |
To create an ECH:
- Click + to create a new ECH.
- Enter the required data in the pop-up window. See the table below.
- Click Save when done.
The new ECH will be created, and you will be redirected to the detail page of the ECH that was just created.
Field | Description |
---|---|
Equipment ID | This field is auto populated based on the object from which you are creating the ECH. |
Condition Date | The date of the Event. This becomes the Last Inspection Date (LID) for the Schedule being credited. |
Responsible Person | This is an important data field. Don’t credit Schedules done by two or more inspectors on one ECH. For example, if one inspector performs the Inspection schedule for cracking on the top head and another inspector performs the Inspection schedule for a non-intrusive external visual inspection, then two ECHs should be created. |
Current Event | This is field that can be queried, which indicates when the event took place. Options are:
|
Conclusion | Note: This field is not configured for all sites and may thus not be available. |
Labels | Custom labels which can be assigned to each record. |
Description | This is a one-line description of the event that will display on the list of condition histories so that easily can be identified what the ECH is all about. E.g., Intrusive cracking inspection of the top head. |
Supervision | Applicable when Witnessing is enabled. |
Authority | Applicable when Witnessing is enabled. |
Now you can start with Step B: Detailing the ECH.