There are some specific cases where the S-RBI assessment approach in IMS PEI changes, depending on the Equipment/Component type.
This section gives guidance for Underground Piping.
This section gives guidance for Underground Piping.
Define Asset – Step 1
See Step 1.
Underground piping can be modelled with Component Type: "Piping UG".
Assign DMs to Component – Step 3
See Step 3.
The applicable Degradation Mechanism is: "Soil Corrosion (AR)".
RL – Step 6 & Step 11
You can use the soil corrosion calculator.
IF – Step 11
See Step 11.
The Interval Factor is generated from the “full life” table.
Barrier Verification – Step 12 & Step 13
Some of the NDE techniques to inspect these areas are smart pigging and guided wave technology.