July 2025
Release 4.4
Note: These Release Notes only cover specific PEI enhancements. All other enhancements, not related to specific disciplines, are described in the IMS Platform (General) Release Notes.
CML Must get Logic Improvements
We’ve updated the way the “Must Get” flag is synchronized between Measurement Sets (MSETs) and Corrosion Measurement Locations (CMLs). Previously, unticking the “Must Get” checkbox on any Measurement within a MSET would automatically untick the “Must Get” checkbox on the associated CML.
Now, the “Must Get” flag on a CML is used to indicate expectation or a plan for the measurement set. Meaning, when a measurement set gets created, the “Must Get” indication on CML is taken as a template to generate the measurement set, indicating measurements are required for the specific CML. However, if the “Must Get” attribute gets changed in the MSET, the value on the CML remains unchanged.

If a CML is marked as "Must get" on creation, but the "Must get" of the associated Measurement Point(s) is unchecked , clicking the Calculate Measurement Set button will trigger issue a message: "Detected measurements have "Must Get" set to false, although they are marked as required at the CML level. Please review your data.” Despite this warning, you can still proceed with the calculation even if these unchecked measurements are left empty. The requirement for mandatory measurements is now determined at the Measurement level, not by the CML's "Must get" setting.

User Instructions
To find out more about editing MSETs, see: Managing Measurement Sets.
To learn more about the “Must Get” checkbox, see: PEI Circuits - Details Page.
New User-Defined Queries for On-Stream Inspection Monitoring
IMS now includes two new User-defined Queries that are designed to enhance the monitoring of on-stream Inspections for Pipe Equipment with precise progress regarding details from the NDT workflow. These queries not only allow you to determine the number of pending or completed NDT inspections but also provide precise progress tracking, incorporating detailed information from the NDT workflow of Planned Events.
Measurement Set With Full NDT Data offers a complete overview of all Measurement Sets, including key details such as Site, Plant, Unit, Floc, Equipment, Circuit, Measurement Set, and Planned Event information. NDT data is sourced from Planned Event Measurement Sets (specific to MIDAP sites).

Measurement Set With Full NDT Data
Measurement Set With NDT Data per Latest Measurement Set displays only the most recent Measurement Set for each Circuit, providing the same detailed information as the "Full NDT Data" query but limited to the latest set.

Measurement Set WIth NDT Data per Latest Measurement Set
User Instructions
To find find out how to use Queries see: IMS Queries.
To learn more about Measurement Sets see: Managing Measurement Sets.