PLSS Schedule Deferral Feature Added
It is now possible to defer Schedules in IMS PLSS which was available in IMS PEI only. Users with a CSA role can enable this feature in Settings \ Maintenance \ Configuration \ Application Settings \ Schedule deferral integrated by entering the number “49” in the N value field.

User Instructions
To learn more about Schedule Integrated Deferrals in IMS, see: Integrated Deferral Approval Process for Schedules.
Remedial Action Import
In the PLSS Remedial action menu, a new section has been added that allows you to import Planned Repairs.
.png?sv=2026-02-06&spr=https&st=2026-10-28T16%3A01%3A22Z&se=2026-10-28T16%3A12%3A22Z&sr=c&sp=r&sig=rpLnYAs9TILEvOiCEvk%2FaoyTg27SPkz8X8uasH5%2F%2FkM%3D)
To use this feature, you can export the template in Excel format, fill it in with the necessary information, and then import it back via the Settings / Data Transfer / Import Data option.
A new option, "PL Remedial Repairs," has been added to the Import Menu.
.png?sv=2026-02-06&spr=https&st=2026-10-28T16%3A01%3A22Z&se=2026-10-28T16%3A12%3A22Z&sr=c&sp=r&sig=rpLnYAs9TILEvOiCEvk%2FaoyTg27SPkz8X8uasH5%2F%2FkM%3D)
User Instructions
To learn more about Remedial Actions see: Remedial Actions.